Minnesota Department of Transportation

511 Travel Info

Hwy 220

East Grand Forks

2024 Construction

Highway 220 East Grand Forks Project Map
A construction project in 2024 includes a concrete resurfacing of nine miles of Highway 220 north of East Grand Forks

Summary of work

Highway 220 between Polk County Road 19 in East Grand Forks and County Road 22 / 23

  • Reconstruct highway to a concrete road
  • Culvert replacements

Traffic Impacts

  • Detour
    • Traffic will detour onto County 66 via 150th St and County 23
    • The detour will be in place for about three months and could have an impact on Harvest.
    • It is expected to begin in May and last through August

It takes longer to construct a concrete road, but it will result in a more durable and longer lasting driving surface.

Learn more

We will hold a public meeting in the spring where participants can meet the project team and ask questions.

Highway 220 East Grand Forks Project Map
Two construction projects will take place near East Grand Forks in 2024 on Highway 220 and Highway 75. Each of the projects has a separate detour.

Nearby projects

A separate project on Hwy 75 north of Crookston requires a detour to construct a roundabout at the intersection with County 21.

The detour for that project is on County 19, 20 and 23. This map shows both projects together.