2026 roadwork ahead

MnDOT will improve Hwy 25 from Catlin St. in Buffalo to Kjellberg Ct. in south Monticello, Wright County. Roadwork will be in 2026 and will require detours.
MnDOT is in the process of developing the final design and traffic plans.
Latest news
- Public meetings set for Thu, Oct. 9, 2025, to highlight 2026 work plans
- Sign up for roadwork email updates
Summary of work
- Reconstruct the road surface from Catlin St. to north of Davidson Ave., includes shoulders and turn lanes
- Replace pipes and improve ditch drainage
- Improve to/from access on Hwy 25 at:
- U-turn south of Kjellberg Ct. (extend shoulder called a 'loon')
- South junction Wright Co. Rd. 131
- 55th St.
- Westridge Ct.
- 3rd Ave.
- Anderson Ave.
- Construct a roundabout at Hwy 25 and Co. Rd. 37
- Construct a roundabout at Catlin St. in Buffalo
- Wright County to construct a roundabout at Hwy 25 and Co. Rd. 113 in 2026