Non-National Highway System culverts
MnDOT District 6
MnDOT replaces or rehabilitates most culverts (greater than 10 feet) in conjunction with other projects. However, MnDOT will occasionally select a culvert for a standalone rehabilitation or replacement project.
MnDOT scores culvert condition needs when selecting projects to include in the 10-year Capital Highway Investment Plan. Culverts that carry roads on the National Highway System (NHS) are scored and selected separately from culvert needs off the system. MnDOT’s approach to managing culvert condition follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.
Non-NHS culverts are scored statewide, but prioritized within each district. The selection of standalone culvert projects is informed by district staff, experts from MnDOT’s bridge office and the Bridge Replacement and Improvement Management System (BRIM).
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-culvert work may be added to a culvert project or a culvert project may be combined with a nearby pavement project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.
What’s been selected?
Related links
- District 6 project selection
- National Highway System culvert projects
- National Highway System bridge projects
- District 6 Non-National Highway System bridge projects
- Pedestrian bridge rehabilitation/replacement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated October 2021
Total score | Bridge number | Route | Key Intersection or Closest Landmark | Work Type | Year planned | High Level cost estimate for planning purposes | Comments |
---|---|---|---|---|---|---|---|
80 | 91155 | US 14 | Bluff ave near St. Charles | 2031 | Replace | $200,000 | |
70 | 3937 | MN 43 | Channel between Gilmore creek and Lake Winona | 2022 | Replace | $400,000 | |
64 | 8453 | US 218 | North of 120th St near Lawrence Township | Not Selected | Replace | $300,000 | |
64 | 8842 | MN 26 | South of Spring Hills Dr near Brownsville | Not Selected | Replace | $200,000 | |
62 | 8648 | MN 56 | North of Little Cannon River near Nerstrand | 2025 | Replace | $200,000 | |
61 | 6108 | MN 44 | East of Dix Dr near Hokah | Not Selected | Replace | $800,000 | Not a district priority. Will continue to monitor culvert performance |
61 | 8489 | MN 56 | Stream west of Upper Iowa River near Le Roy | 2026 | Replace | $300,000 | Selected prior to policy (in 2019-2028 CHIP) |
60 | 689 | MN 16 | Pine Creek | Not Selected | Replace | $300,000 | Not a district priority. Will continue to monitor culvert performance |
59 | 89344 | MN 56 | North of Jct I-90 near Austin | Not Selected | Replace | $300,000 | |
59 | 91122 | MN 43 | North of Heartwood Dr near Lewiston | 2031 | Replace | $100,000 | |
57 | 20X01 | MN 57 | North of 600th St near Mantorville | Not Selected | Replace | $200,000 | Not a district priority. Will continue to monitor culvert performance |
57 | 8676 | MN 60 | East of County 55 Blvd near Zumbrota | 2022 | Replace | $300,000 | Selected prior to policy (in 2019-2022 STIP) |
57 | 8885 | MN 30 | East of SW 62nd Ave near Ellendale | 2029 | Replace | $100,000 | Selected prior to policy (in 2019-2028 CHIP) |
55 | 8055 | US 14 | West of Chester Ave near Rochester | Not Selected | Replace | $100,000 | |
52 | 6033 | US 14 | East of County Road 102 SE near Eyota | Not Selected | Replace | $300,000 | |
51 | 3225 | US 14 | West of Sportsman Rd near Lewiston | Not Selected | Replace | $600,000 | |
51 | 4988 | US 14 | Whitewater River | 2026 | Replace | $500,000 | Selected prior to policy (in 2019-2028 CHIP) |
51 | 4989 | US 14 | Whitewater River | 2026 | Replace | $500,000 | Selected prior to policy (in 2019-2028 CHIP) |
51 | 6025 | US 14 | East of County Road 20 near Stockton MN | Not Selected | Replace | $400,000 | |
51 | 6028 | US 14 | Whitewater River | 2028 | Replace | $300,000 | Selected prior to policy (in 2019-2028 CHIP) |
51 | 6032 | US 14 | Whitewater River | 2028 | Replace | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
51 | 8049 | US 14 | North of Garvin Brook near Stockton | Not Selected | Replace | $200,000 | |
51 | 8050 | US 14 | East of Eagle Blvd near St. Charles | 2026 | Replace | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
51 | 8053 | US 14 | Stream connecting South fork Whitewater River to irrigation ditch near St. Charles | 2026 | Replace | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
51 | 88951 | US 218 | South of Rose Creek near Austin | Not Selected | Replace | $300,000 | |
51 | 91119 | US 14 | South of Sportsman Dr near Lewiston | Not Selected | Replace | $500,000 | |
51 | 91120 | US 14 | South of Sportsman Dr near Lewiston | Not Selected | Replace | $500,000 | |
51 | 91148 | US 14 | South of Dutchmans Crossing near Lewiston | Not Selected | Replace | $400,000 | |
49 | 6934 | MN 247 | Silver Spring Creek | 2026 | Replace | $300,000 | Selected prior to policy (in 2019-2028 CHIP) |
49 | 8669 | MN 42 | South of County Road 2 NE near Viola | 2026 | Replace | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
49 | 91121 | MN 43 | South of Hart Township Road near Lewiston | 2031 | Replace | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
47 | 8917 | MN 26 | At Shellhorn Dr near Brownsville | Not Selected | Replace | $300,000 | |
47 | 92572 | MN 248 | East of Quarry Hill Dairy near Rollingstone | Not Selected | Replace | $300,000 | |
45 | 6119 | US 52 | North of 320th St near Chatfield | 2026 | Replace | $400,000 | Part of a mill and overlay project |
37 | 55 | MN 43 | Stream near Rushford Village | Not Selected | Replace | $400,000 | |
36 | 8841 | MN 60 | Cold Creek | 2022 | Replace | $500,000 | Selected prior to policy (in 2019-2022 STIP) |
16 | 6029 | US 14 | East of 140th Ave SE near Dover | 2028 | Replace | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
16 | 6030 | US 14 | S FK WHITEWATER RIVER | 2028 | Replace | $300,000 | Selected prior to policy (in 2019-2028 CHIP) |
16 | 6031 | US 14 | Whitewater River | 2028 | Replace | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
16 | 8051 | US 14 | Whitewater River | 2026 | Replace | $100,000 | Selected prior to policy (in 2019-2028 CHIP) |
16 | 8052 | US 14 | West of West Ave near St Charles | 2026 | Replace | $100,000 | Selected prior to policy (in 2019-2028 CHIP) |
14 | 8675 | MN 42 | South of County Road 2 NE near Viola | 2026 | Replace | $300,000 | Selected prior to policy (in 2019-2028 CHIP) |
1 | 8890 | MN 60 | Stream near Zumbro Falls | 2022 | Replace | $300,000 | Part of a mill and overlay project |