Minnesota Department of Transportation

511 Travel Info

Project selection

Increasing the transparency of how we select highway construction projects

Safety programs

Highway Safety Improvement Program

Greater Minnesota (state projects)

Scoring criteria for the Highway Safety Improvement Program in Greater Minnesota. A total of 100 points is available spread equally between five criteria: location screening, coverage, expected impact, planning, and alignment with program goals.

The Highway Safety Improvement Program (HSIP) funds cost effective construction projects that reduce fatalities and serious injuries on all public roads. In Greater Minnesota, MnDOT administers two HSIP programs: one focused on safety improvements to local roads and a second focused on safety improvements to state highways. The majority (60 percent) of HSIP funding goes to local roads. This page only applies to the state highway program.

Project proposals are solicited from MnDOT districts in two categories: proactive/systemic projects that address known risk factors and reactive projects that address a sustained crash location. Most projects are originally identified in a district or county safety plan or an analysis of fatal and serious injury crashes on the state highway network.

What’s been selected?

Related links

How the projects scored

Below are the results of the latest round of HSIP announced in spring 2022. Projects needed to score at least 50 points to be considered for funding.

Last updated June 2023

Project Score District Route Year Planned Description Federal Total Local match Total Project Cost Comments
1 4 I-94 2025 I-94 WINTER WEATHER ADVISORY SYSTEM IN MOORHEAD $440,000 $48,888 $488,888 Recommend awarding Sec164 funds toward shovel-ready project to ensure all used for traffic safety
60 1 TH-169 2028 ROUNDABOUT AT TH-169/CSAH-67 (4TH AVE SE) $3,600,000 $400,000 $4,000,000
55 1 TH-169 2028 TH-169/TH-73/IRON WORLD RD ROUNDABOUT $3,150,000 $350,000 $3,500,000 Not awarding Sec164 funds in 2028
86 1 TH-2 2026 6-INCH GIWR ON TH-2 FROM DEER RIVER TO COHASSET $427,500 $47,500 $475,000
58 1 TH-53 2025 HTCB ON TH-53 FROM EXISTING TERMINUS TO CSAH-132 $472,500 $52,500 $525,000
54 2 TH-92 2027 WIDEN/PAVE SHOULDERS ON TH-92 $1,600,000 $1,200,000 $2,800,000
55 3 TH-23 2028 J-TURN AT TH-23/BEL CLARE DR $1,080,000 $120,000 $1,200,000
50 3 TH-371 2028 J-TURN AT TH-371/CSAH-29 $1,800,000 $200,000 $2,000,000
72 3 TH-47 2028 TH-47/CSAH-5 ROUNDABOUT $2,250,000 $250,000 $2,500,000 Not awarding Sec164 funds in 2028 (PRIOR APPROVAL: Nov22_D3-09)
41 3 TH-47 2028 TH-47/CSAH-8 ROUNDABOUT $2,250,000 $250,000 $2,500,000 Not awarding Sec164 funds in 2028 (PRIOR APPROVAL: Nov22_D3-09)
60 3 TH-55 CHIP TH-55/CSAH-14 ROUNDABOUT $2,250,000 $250,000 $2,500,000 Recommend funding 2029 project as future targets become available
63 3 TH-10 CHIP TH-10 J-TURN CORRIDOR IN BIG LAKE, MN $1,800,000 $1,200,000 $3,000,000 Recommend funding 2029 project as future targets become available
55 3 TH-97 CHIP TH-95/CSAH-7 ROUNDABOUT $2,250,000 $250,000 $2,500,000 Recommend funding 2029 project as future targets become available
47 3 TH-6 CHIP TH-6/CSAH-11 ROUNDABOUT $2,250,000 $250,000 $2,500,000 Recommend funding 2029 project as future targets become available
43 3 TH-6 CHIP TH-6/CSAH-30 ROUNDABOUT $2,250,000 $250,000 $2,500,000 Recommend funding 2029 project as future targets become available
43 4 TH-10 2028 TH-10 J-TURN CORRIDOR IN BECKER AND OTTER TAIL COUNTIES $3,000,000 $300,000 $3,300,000 Not awarding Sec164 funds in 2028
99 4 Various 2026 CENTERLINE RUMBLE STRIPS ON 2-LANE HIGHWAYS $700,000 $70,000 $770,000
92 4 I-94 2027 6-INCH GIWR ON VARIOUS TRUNK HIGHWAYS $1,000,000 $10,000 $1,010,000
93 6 TH-52 2026 HTCB ON TH-52 FROM NORTH OF CSAH-7 TO SOUTH OF CSAH-9 $1,620,000 $509,800 $2,129,800
93 6 TH-52 2027 TH-52 FROM ZUBROTA TO CANNON FALLS (NORTH) HIGH TENSION CABLE BARRIER $1,620,000 $541,100 $2,161,100 Insufficicent funds available
54 6 TH-44 2027 ROUNDABOUT AT TH-44/TH-76/KINGSTON ST $3,412,515 $666,000 $4,078,515
71 7 TH-60 2026 TH-60 ROAD DIET IN WINDOM $1,180,000 $120,000 $1,300,000
61 8 TH-23 2027 SKEW REALIGNMENT AT TH-23/TH-67 $504,000 $56,000 $560,000
61 8 TH-23 2026 LED STOP SIGN AT TH-23/TH-7 $396,000 $44,000 $440,000
41 8 TH-19 2027 TH-19/CSAH-1 LEFT TURN LANE $1,800,000 $200,000 $2,000,000 Insufficicent funds available
18 8 TH-67 2025 INTERSECTION LIGHTING ON TH-67 $81,000 $9,000 $90,000
47 8 TH-23 N/A TH-23/TIGER DR J-TURN $2,520,000 $280,000 $2,800,000 District submitted for a preliminary score based on alternatives analysis
42 8 TH-23 N/A TH-23/TIGER DR ROUNDABOUT $3,465,000 $385,000 $3,850,000 District submitted for a preliminary score based on alternatives analysis
68 8 TH-23 N/A TH-71 J-TURN CORRIDOR IN EAGLE LAKE, MN $4,500,000 $500,000 $5,000,000 District submitted for a preliminary score based on alternatives analysis