Increasing the transparency of how we select highway construction projects

National Highway System pavement projects

MnDOT District 6

How the projects scored in 2019

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2019

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
98 I-35 Concrete repaving northbound from Rice County Road 9 to Heath Creek Rest Area $10,000,000 2029  
97 I-90 Thick overlay from Highway 105 to Mower County Road 46 $8,000,000 2028  
93 I-90 Medium mill and overlay from Mower County Road 1 to east of Highway 63 $3,500,000 2023  
93 I-90 Medium mill and overly from I-90 from Highway 76 to Nodine $4,400,000 2029  
90 US61 Medium mill and overlay northbound lanes from Highway 14 to Highway 42 and southbound lanes from Highway 14 to Highway 248 $15,000,000 2028  
90 I-35 Medium mill and overlay from from Rice County Road 2 to Rice County Road 48 $13,000,000 2029  
85 I-90 Medium mill and overlay from Highway 74 to Highway 43 $6,500,000 2026  
85 I-90 Thick overlay from Mower County Road 46 to Highway 16 $10,000,000 2027  
85 US52 Medium overlay from Highway 63 to 85th St $16,000,000 Not selected Not a current district priority, continue to monitor pavement performance
84 I-35 Unbonded overlay from Rice County Road 48 to Highway 21. $11,500,000 2024  
83 I-90 Medium mill and overlay from Highway 63 to east of Olmsted County Road 19 $6,400,000 2027  
83 US14 Medium mill and overlay from Byron to Rochester $4,200,000 2028  
80 US61 Medium mill and overlay from Highway 292 to Redwing $1,800,000 Not selected Not a current district priority, continue to monitor pavement performance
78 US52 Reconstruction from Highway 19 to near Highway 60.  $30,000,000 2021 Project will be competed with a bridge project replacing 6 bridges
78 US14 Medium mill and overlay from Marion Road in Rochester to Olmsted County Road 19 west of Chester Woods Park $3,000,000 2023  
78 US61 Medium mill and overlay from Highway 19 to Goodhue County Road 18 $2,500,000 Not selected Not a current district priority, continue to monitor pavement performance
77 I-35 Medium mill and overlay from Straight River to Highway 14 $3,500,000 2029  
75 US218 Medium mill and overlay from Highway 30 to Highway 14 $6,300,000 2024  
75 MN43 Medium mill and overlay from I-90 to Highway 61 $4,000,000 2029  
73 US52 Thick overlay from Highway 60 to Goodhue County Road 7 $1,900,000 2023  
70 US52 Medium mill and overlay from Highway 80 to Fillmore County Road 5 $3,800,000 2026 Project will be completed with a bridge project replacing 6 box culverts.
57 I-35 Medium mill and overlay Highway 30 to north of Bridge 74803 In Steele County $3,700,000 2024
55 I-90 Unbonded overlay from Mower County Road 46 to Highway 16 $21,000,000 2028 Pavement condition anticipated to be to deteriorate faster tham model predicts
54 I-90 Unbonded overlay from Mower County Road 46 to Highway 105 in Austin $12,000,000 2022 Pavement condition anticipated to be to deteriorate faster tham model predicts
54 I-90 Medium mill and overlay from Winona County Road 12 to Highway 61 near Dakota $3,900,000 2023 Selected prior to policy (in 2019-2028 CHIP)
50 US52 Unbonded overlay from Olmsted County Road 12 to south junction of Highway 60 $15,000,000 2027 Selected prior to policy (in 2019-2028 CHIP)
50 US 61 Medium mill and overlay from Homer to Winona $7,500,000 2027 Selected prior to policy (in 2019-2028 CHIP)
47 I-90 Unbonded overlay westbound lanes from Alden to Highway 13 $13,000,000 2025 Selected prior to policy (in 2019-2028 CHIP)
38 I-35 Thick overlay from Rice County Road 9 to Heath Creek Rest Area $4,800,000 2029 Selected prior to policy (in 2019-2028 CHIP)
38 I-35 Thick overlay from Rice County Road 9 to Heath Creek Rest Area $4,800,000 2029 Selected prior to policy (in 2019-2028 CHIP)
35 US14 Unbonded overlay from Byron to Rochester $15,000,000 2029 Selected prior to policy (in 2019-2028 CHIP)
34 I-90 Unbonded overlay from Highway 43 to Highway 76 $11,500,000 2026 Selected prior to policy (in 2019-2028 CHIP)
34 I-90 Unbonded overlay from Highway 43 to Highway 76 $11,500,000 2026 Selected prior to policy (in 2019-2028 CHIP)