How the projects scored in 2019

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2019

Score Community Route Description  High-Level Cost Estimate for Planning Purposes  Year Planned (FY) Comments
87 Northfield MN246 Potential pavement project in Northfield $5,700,000 Not selected Additional coordination needed to better understand local needs and timeline.
86 Stewartville US63 Future pavement project from south of 6th St SE to the Root River $500,000 Not selected Additional coordination needed to better understand local needs and timeline.
84 Winona MN43 Resurfacing from Sarnia St to end of Mississippi River bridge $3,200,000 2025
83 Mantorville MN57 reconstruction from Zumbro River bridge to 9th St in Mantorville $3,100,000 2023
83 Albert Lea US65/MN13 Future pavement project from S Shore Drive to Main St to Euclid Ave $24,000,000 Not selected Additional coordination needed to better understand local needs and timeline.
82 Spring Valley MN16 Reconstruction from Tracy Road to Griswald St 2026
82 Plainview MN247 Future pavement project from 10th St to Highway 42 $400,000 Not selected Additional coordination needed to better understand local needs and timeline.
81 Lanesboro MN250 Future pavement project from Highway 16 to the Root River $3,600,000 Not selected Additional coordination needed to better understand local needs and timeline.
79 Northfield - Carleton MN19 Future pavement project of Highway 19 from Highway 3 to eastern city limits in Northfield $1,000,000 Not selected Additional coordination needed to better understand local needs and timeline.
77 Houston MN16 Reconstruction through Houston $6,000,000 2024
77 Dundas/Northfield MN3 Future pavement project from Rice County Road 20 to the Cannon River $2,600,000 Not selected Additional coordination needed to better understand local needs and timeline.
77 Austin MN105 Future pavement from Turtle Creek to I-90 $1,000,000 Not selected Additional coordination needed to better understand local needs and timeline.
77 Red Wing US61 Future pavement project from Old Main St to Bench St $1,000,000 Not selected Additional coordination needed to better understand local needs and timeline.
75 Cannon Falls  MN19 Future pavement project from Highway 52 to Highway 20 $400,000 Not selected Additional coordination needed to better understand local needs and timeline.
75 Albert Lea US69 Future pavement project from 9th St to Highway 13 $600,000 Not selected Additional coordination needed to better understand local needs and timeline.
73 Blooming Prairie US218 Reconstruction from 3rd St NE to Highway 30 on the north side of town $6,000,000 2023
71 Altura MN248 Future pavement project from 1st Ave SE to 3rd Ave NE $200,000 Not selected
69 Faribault MN298 Future pavement project in Faribault $300,000 Not selected
69 Brownsdale MN56 Future pavement project from 260th St to 2 blocks north of Lathan St $400,000 Not selected
67 La Crescent US61/MN16 Future pavement project from S 14th St to N 4th St $1,200,000 Not selected
67 Lake City US63 Future pavement project from Orchard Lane to Highway 61 $6,900,000 Not selected
66 Harmony MN139 Future pavement project from 9th St SW to Highway 52 $500,000 Not selected
66 Hokah MN44 Future pavement project from 6th St to Highway 16 $600,000 Not selected
65 Red Wing MN58 Medium mill and overlay from 21st St to US 61 in Red Wing $1,800,000 2021 Selected in 2021 due to pavement condition. A future reconstruction project is being planned which will include ADA improvements and local utility needs.
65 Le Roy MN56 Reconstruction from east city line to 0.4 miles north of 770th Ave $8,700,000 2023 Selected in 2023 to match year of available city funding.
65 Northfield MN3 Future pavement project from the Cannon River to the railroad bridge north of St Olaf Ave $400,000 Not selected
64 Faribault MN3 Future pavement project from Highway 21 to north of 2nd Ave NW intersection $600,000 Not selected
64 Faribault - Riverside MN60 Future pavement project from Central Ave to the Straight River bridge $400,000 Not selected
62 Rochester US14 Medium mill and overlay from Highway 52 to Olmsted County Road 36 $3,500,000 2023 Project selected due to pavement wearing down faster than expected, plus there are necessary signal, bicycle, and pedestrian upgrades needed here.
62 Nerstrand MN246 Future pavement project from Poplar St to Lamb Ave $300,000 Not selected
60 Cannon Falls MN19 Medium mill and overlay from Highway 20 to Almond St in Cannon Falls $2,000,000 2022 Selected in 2022 due to pavement condition and needed ADA improvements.
60 Elgin MN42 Future pavement project from the Whitewater River to Dry Creek $300,000 Not selected
59 Wabasha MN60 Future pavement project from Highway 61 to the Mississippi River bridge $700,000 Not selected
56 Kenyon MN56 Future pavement project including Home St to Highway 60 and Highway 60 to Trondheim Road $300,000 Not selected
54 West Concord MN56 Resurfacing from Southview St to Dodge County Road 24 $1,000,000 2023 Selected prior to policy (in 2019-2028 CHIP)
54 Faribault MN299 Future pavement project in Faribault $400,000 Not selected
52 Spring Grove MN44 Future pavement project from 3rd Ave NW to 4th Ave SE $400,000 Not selected
45 Caledonia MN44 Medium mill and overlay in Caledonia $500,000 2024 Coordinated with a larger pavement project
44 Adams MN56 Future pavement project from 1st St to 5th St $200,000 Not selected
44 Albert Lea MN13 Future pavement project from Euclid Ave to the Skyline Plaza entrance $400,000 Not selected
38 Spring Valley  US63 Future pavement project from Fillmore County Road 12 to Highway 16 $300,000 Not selected
36 Red Wing US61 Future pavement project from Potter St to Old Main St $300,000 Not selected