The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2019

Score Route Description High level construction cost estimate for planning purposes  Year Planned (FY) Comments
98 US169 Medium mill and overlay from Minnesota River to north of Highway 14 $5,700,000 2027
96 US169 Unbonded overlay from Blue Earth County Road 115 combining with Highway 169, and extending to the Riverfront Drive bridge $26,500,000 2029  
94 I-90 Major concrete rehabilitation from South Dakota border to Rock River $11,400,000 2022  
93 I-90 Medium overlay eastbound from east of Highway 4 to Highway 15 $5,400,000 2022  
93 I-90 Medium overlay eastbound from the Rock River to Rock/Nobles county line $3,600,000 2029  
92 I-90 Medium overlay westbound lanes from Jackson Couty Road  5 bridge to Highway 60 $4,000,000 2029  
90 MN15/MN60 Unbonded overlay from western junction of Highway 60 to eastern junction of Highway 60 in Madelia $16,000,000 2024  
89 US14 Thick mill and overlay Highway 15 to west of Highway 111 $12,000,000 2021  
89 MN60 Medium mill and overlay eastbound lanes from east of Highway 15 bridge to  east of Blue Earth County Road 109 $3,200,000 2022  
89 MN60 Unbonded overlay from Laclaire Street to Blue Earth County Road 115 west of Highway 169 intersection (Cray Corner) $11,000,000 2029 Coordinated with adjacent Highway 169 segment into Mankato
89 MN60 Major concrete repair eastbound lanes from I-90 to Jackson County Road 24 $7,500,000 2029  
88 MN60 Medium mill and overlay westbound lanes from Nobles County Road 47 to north of I-90 $6,300,000 2029  
87 I-90 Medium overlay eastbound lanes from Rock/Nobles county line to Nobles County Road 35 $2,700,000 2029  
87 US169 Minor concrete rehabilitation from Highway 14 to Highway 99 $3,800,000 Not Selected Will continue to monitor for an increased rate of deterioration of the pavement
85 US14 Unbonded overlay from Lookout Bridge to Highway 22 $20,000,000 Not Selected Project is being developed for potential future funding, which may include bridge and interchange improvements
85 US14 Minor concrete rehabilitation from 2 miles west of Highway 111 to Lookout Drive $2,500,000 Not Selected Will continue to monitor for an increased rate of deterioration of the pavement
83 I-90 Medium overlay eastbound lanes from Rock County Highway 4 to the Rock River $3,500,000 2022
83 I-90 Medium overlay westbound lanes from railroad bridge near Rushmore to Nobles County Road 35 $3,700,000 2025 Aligns with Nobles County bridge projects
83 I-90 Medium overlay westbound lanes from east of Highway 60 to east of Nobles County Road 13 $5,900,000 Not Selected Waiting to coordinate with another project. 
83 I-90 Medium overlay westbound lanes from Highway 15 to east of Highway 4 $7,100,000 Not Selected Waiting to coordinate with another project. 
83 I-90 Thick overlay westbound lanes from the Rock/Nobles County line to the Rock River $6,100,000 Not Selected Waiting to coordinate with another project. 
83 MN60 Unbonded overlay from west of Cottonwood County Road 47 to Watonwan County Road 5 near Butterfield $17,500,000 Not Selected Waiting to coordinate with another project. Already extensive work on Highway 60 planned in the southwest portion of the district
82 US14 Minor concrete rehabilitation from Blue Earth County Road 37 at Smith's Mill to Waseca County Road 2 overpass $5,000,000 Not Selected Waiting to coordinate with another project. Can potentially be fixed through an IDIQ contract
81 US14 Medium overlay from Highway 71 to east Springfield city limits $5,900,000 2022
81 US71 Medium overlay from Iowa border to Riverside Drive in Jackson $4,300,000 2028
80 US169 Thick mill and overlay from Ramsey Street to Union Street in St. Peter $600,000 2022
80 US14 Major concrete rehabilitation from Highway 22 to Highway 60 $10,700,000 2026
80 MN60 Major concrete rehabilitation eastbound and westbound lanes of the Heron Lake bypass and westbound lanes between Alder Street in Wilder and the Heron Lake bypass.  $9,700,000 2029
80 MN60 Minor concrete rehabilitation from Nobles County Road 4 to I-90 $2,100,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
79 US169 Medium overlay Iowa border to Faribault County Road 52 $7,100,000 2023
79 MN60 Major Concrete rehabilitation westbound lanes from Jackson County Road 24 to Nobles County Road 47  $7,200,000 2029
78 US71 Thin mill and overlay from Highway 60 to Highway 30 $2,900,000 2020
78 I-90 Unbonded overlay eastbound lanes from Jackson County Road 5 bridge to Highway 86 $14,000,000 2021
78 MN60 Medium mill and overlay from Blue Earth County Road 20 to Laclaire Street  $3,500,000 2024
78 I-90 Medium overlay eastbound lanes from Highway 86 to Highway 4 $11,000,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
77 US169 Major concrete rehabilitation from Winnebago to Vernon Center $15,000,000 2027
77 I-90 Major concrete rehabilitation Jackson County Road 35/Minnesota Southern railroad bridge to Rock/Nobles County line $4,800,000 Not Selected Waiting to coordinate with another project--potentially with another I-90 project in 2025
77 MN22 Thick overlay from south ramps of Highway 14 to Blue Earth County Road 26 $2,900,000 Not Selected Waiting to coordinate with a larger Highway 22 project in Mankato
76 US14 Minor concrete rehabilitation from Waseca County Road 2 overpass to Steele County line $6,000,000 Not Selected Removed from CHIP due to projects with higher scores and this project could be potentially addressed with an IDIQ contract
76 MN60 Major concrete rehabilitation from Alder Street to Highway 62 $17,000,000 Not Selected Already extensive work on Highway 60 in the southwest portion of the district, and adjacent to future Windom project
76 US169 Medium mill and overlay from Leland Parkway to I-90 $1,600,000 Not Selected Waiting to Coordinate with pavement work in Blue Earth County
75 US71 Medium overlay from 120th Street (Sanborn north city limits) to Highway 14 $600,000 Not Selected Small segment that should be wrapped up into larger adjacent projects. Coordinating with District 8.
75 US169 Unbonded overlay from Commerce Street (former Highway 112) to Nicollet County Road 28 $5,800,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
74 MN60 Unbonded overlay from Watonwan County Road 5 near Butterfield to Highway 4 $8,400,000 2028 Selected prior to policy (In 2019-2028 CHIP)
74 US14 Medium mill and overlay from Palmer Avenue roundabout to Garden Street in New Ulm $2,800,000 Not Selected
74 MN60 Minor Concrete rehabilitation from Iowa border to Nobles County Road 4  $700,000 Not Selected
73 US71 Medium mill and overlay from I-90 to Jackson County Road 34 $500,000 2020 Selected prior to policy (In 2019-2022 STIP)
73 MN60 Unbonded overlay westbound lanes from 0.4 miles east of Cottonwood County Road  47 to 0.3 miles west of Cottonwood County Road 47 west of Mountain Lake $1,100,000 2023 Selected prior to policy (In 2019-2022 STIP)
73 MN22 Reconstruction from Riverfront Drive  to north end of railroad bridge $4,900,000 2024 Selected prior to policy (In 2019-2028 CHIP)
73 MN60 Unbonded overlay eastbound lanes from Jackson County Road 24 to Alder Street in Wilder $8,600,000 2029 Project previously identified in the 2019-2028 CHIP and aligns with higher-scoring Highway 60 project between Heron Lake and Worthington. 
73 US169 Major concrete rehabilitation from Blue Earth County 13 to Highway 60 $8,400,000 Not Selected
72 US71 Thick overlay from Highway 30 to 120th Street (Sanborn north city limits) $10,000,000 Not Selected
72 US14 Minor concrete rehabilitation from Highway 60 eastern junction to Blue Earth County Road 37 at Smith's Mill $1,400,000 Not Selected
72 MN22 Medium mill and overlay Blue Earth County Road 26 to Riverfront Drive $1,300,000 Not Selected Project previously identified in the 2019-2028 CHIP, but was removed to align with a future Highway 22 project in Mankato
71 US59 Thick overlay from 27th Street N to Highway 62 $12,000,000 2027 Selected prior to policy (In 2020-2029 CHIP)
71 US71 Medium mill and overlay from Riverside Drive to Prospect Street in Jackson $500,000 Not Selected
70 US71 Medium overlay from Jackson County Road 34 to Highway  60 $5,800,000 2020 Selected prior to policy (In 2019-2022 STIP)
70 US169 Medium mill and overlay from 0.7 miles north of I-90 to 1 mile north of I-90 $600,000 Not Selected
69 MN60 Thin mill and overlay eastbound lanes from Watonwan County Road 5 to 690th Lane $1,700,000 Not Selected
68 MN15 Medium mill and overlay from Highway 60 to Brown/Watonwan County line $1,300,000 2023 Selected prior to policy (In 2019-2022 STIP).
68 MN22 Reconstruction from Le Sueur County Road 102 to north end of the Minnesota River bridge $7,600,000 2024 Selected prior to policy (In 2019-2028 CHIP)
68 MN15 Medium mill and overlay from 4th Street to Goemann Road $400,000 Not Selected
68 MN60 Thin mill and overlay eastbound lanes from Watonwan County Road 27 to Watonwan County Road 5 in Butterfield $1,500,000 Not Selected
67 MN15 Medium mill and overlay from east Highway 60 interchange to 1 mile north of Highway 60 $500,000 2023 Selected prior to policy (In 2019-2022 STIP), coordinating with another project
67 MN15 Thin overlay from northeast of Highway 14 to Minnesota Prairie Line railroad west of Winthrop $3,300,000 Not Selected
67 MN22 Medium mill and overlay from the north end of the Minnesota River bridge to Highway 169 in St. Peter $300,000 Not Selected
66 US59 Major concrete pavement repair/diamond grinding from I-90 to north of Prairie Drive in Worthington $400,000 2027 Selected prior to policy (In 2019-2028 CHIP)
66 US59 Major concrete pavement repair/diamond grinding from north of Prairie Drive to 27th Street N in Worthington $400,000 2027 Selected prior to policy (In 2019-2028 CHIP)
65 US14 Medium mill and overlay from northeast of Brown County Road 27 to east of the Palmer Avenue roundabout in New Ulm $5,100,000 Not Selected  
64 MN15 Medium overlay from Brown County Road 24 to Cottonwood Street in New Ulm $3,000,000 Not Selected  
64 MN23 Medium mill and overlay from railroad crossing to Rock/Pipestone county line in Jasper $100,000 Not Selected  
63 MN15 Medium mill and overlay from Goemann Road to Watonwan county line $22,000,000 Not Selected  
63 MN15 Medium overlay from Watonwan/Brown County line to Brown County Road 24 $3,500,000 Not Selected  
62 MN15 Medium overlay from Martin/Watonwan County line to north of 360th Street $3,200,000 2023 Selected prior to policy (In 2019-2028 CHIP)
60 US14 Medium mill and overlay from 7th Avenue NE to northeast of Brown County Road 27 $400,000 Not Selected  
59 MN22 Reconstruction from north end of railroad bridge to south of Le Sueur County Road 102 $15,000,000 2024 Selected prior to policy (In 2019-2028 CHIP)
59 US169 Medium mill and overlay from Faribault County Road 52 to 10th Street in Blue Earth $500,000 Not Selected
58 I-90 Medium overlay from west of Highway 169 to Highway 22 $20,000,000 2028 Selected prior to policy (In 2019-2028 CHIP)
58 I-90 Minor concrete rehabilitation westbound lanes from Highway 86 to Jackson County Road 5 bridge $2,700,000 Not Selected  
57 US14 Medium mill and overlay from west of the CP railroad overpass to western junction with Brown County Road 7 $700,000 Not Selected  
57 US14 Medium mill and overlay from the railroad crossing to 8th Avenue SW in Sleepy Eye $300,000 Not Selected  
56 MN15 Thick mill and overlay from Minnesota Prairie Line railroad to Highway 19 $200,000 2023 Selected prior to policy (In 2019-2022 STIP)
53 I-90 Unbonded overlay eastbound lanes from east of Nobles County Road 13 near Rushmore to Highway  60 $18,000,000 Not Selected  
53 I-90 Unbonded overlay eastbound lanes from Highway 60 to Jackson County Road 5 bridge in Jackson County $16,000,000 Not Selected  
53 US169 Unbonded overlay southbound lanes from north Highway 93 intersection to Union Street in St. Peter $19,000,000 Not Selected  
53 US169 Minor concrete rehabilitation from north Highway 93 intersection to Commerce Street (former Highway 112) in Le Sueur $500,000 Not Selected  
52 I-90 Minor concrete rehabilitation westbound lanes from west of Highway 109 to Highway 22 $1,600,000 Not Selected  
52 I-90 Minor concrete rehabilitation eastbound lanes from Highway 22 to west of Highway 109 $1,600,000 Not Selected  
52 US169 Unbonded overlay from southwest of Le Sueur County Road 28 to Highway 19 $13,300,000 Not Selected  
48 I-90 Unbonded overlay from westbound lanes from east of Highway 4 to east of Highway 86 $36,000,000 Not Selected  
44 MN23 Minor concrete pavement repair from south I-90 ramps to railroad crossing in Jasper $3,700,000 Not Selected  
42 US14 Minor concrete rehabilitation from east Springfield city limits to railroad crossing on the west side of Sleepy Eye $2,400,000 Not Selected  
33 I-90 Major concrete rehabilitation eastbound lanes from Nobles County Road 35/Minnesota Southern railroad bridge to east of Nobles County Road 13 near Rushmore $7,800,000 Not Selected  
29 MN60 Unbonded overlay Eastbound lanes from Blue Earth County 109 to Highway 15 bridge $11,000,000 2022 Selected prior to policy (In 2019-2022 STIP)
25 MN60 Unbonded overlay from Highway 4 to Highway 15 bridge $22,000,000 2020 Selected prior to policy (In 2019-2022 STIP)
25 MN15 Thin mill and overlay from Cottonwood Street to 20th Street S in New Ulm $600,000 Not Selected  
17 US169 Reconstruction from south of Highway 99 to South Minnesota Avenue Frontage road in St. Peter $2,700,000 2023 Coordinating with another MnDOT project