Washington St.—Brainerd

Hwy 210 from Baxter Dr. to Pine Shores Rd., Crow Wing County

Current impacts

Photo of SFD on another job
2026 work areas—East, Mall and Railyard. Select map to enlarge.

Hwy 210

Pine Shores Rd. to Kingwood St.

  • Periodic lane or shoulder closures as crews clear trees, relocate utilities, mobilize equipment and set up 2026 work areas

Latest news

Upcoming impacts

Project minute

Watch a quick clip to learn about this Brainerd construction project in 2026-2027.


Source: MnDOT Youtube

Reconstruct, improve

MnDOT will reconstruct and improve the Washington St. (Hwy 210) through Brainerd from Baxter Dr. to Pine Shores Rd. in 2026 and 2027.

Hwy 210

  • Reconstruct (mall, railyard, downtown, bridge segments) or resurface (east and west segments) the road
  • Reconstruct curbs, gutters, raised medians and storm sewers
  • Update signal systems
  • Remove signal systems at Mill Ave. and 4th Ave. NE
  • Realign and improve access at the Hwy 210 and Hwy 25/Mill Ave., includes two roundabouts
  • Upgrade city utilities beneath the road
  • Upgrade pedestrian sidewalks and approaches and reconstruct/connect the Cuyuna Lakes Trail
  • Update the Mississippi River bridge
Project location map and general segments. Select image to enlarge

Hwy 210 segments

2026 work
  • East— 10th Ave. NE to Pine Shores Rd.
  • Mall—5th Ave. E to 10th Ave. NE
  • Railyard —Kingwood St. to 5th Ave.

2027 work

  • Downtown — E River Rd./N 1st St. to Kingwood St.
  • Bridge— 4th St. NW to east of the Mississippi River at E River Rd./N 1st St.
  • West — Baxter Dr. to 4th St. NW

Work segments subject to change once more is known. More details to become available closer to construction.