About this project
MnDOT is planning to resurface two bridges on Hwy 23, north of Marshall crossing the Redwood River and Threemile Creek near Green Valley
Summary of work
- Resurface bridge decks
- Replace approach panels
- Replace guardrails
Traffic impacts
- A detour is in place for the duration of this project.
- Traffic will be routed to Hwy 19 and CR 9.
Project updates
July 10, 2025
- Crews are making repairs underneath the bridge.