About this project
![Map of Hwy 23 south gap](images/hwy23southgap4.30.21.jpg)
- Expansion of Hwy 23 from New London to Paynesville from two lanes to four lanes.
- Watch a video overview of the project (YouTube).
Traffic impacts
- Work in 2024 will be under traffic, with no planned detours.
- Please use caution through the work zone (see map).
Project updates
July 26, 2024
- The treatment area for the pedestrian underpass is almost complete and it will be installed next week.
- Crews will also begin prepping for the new culvert at Long Lake next week.
- Pipe work continues throughout the project.
- Paving operations for the final segment of roadway are scheduled to begin the week of August 12.
- Work schedules are weather dependent.
Background
Hwy 23 is an important interregional corridor that is a key artery for the economy in the region. It provides the primary east-west route connecting Willmar to Interstate 94 and beyond. The segment of Hwy 23 between Willmar and Interstate 94 is a distance of approximately 53 miles. Of these 53 miles, all but 16 miles have been constructed as a four lane roadway.