Minnesota Department of Transportation

511 Travel Info

Highway 243 Osceola Bridge

Franconia Township MN and Osceola WI

Evaluation process

Summary

Step 1: Does the alternative meet the primary needs of the project? Does the alternative have issues that make it unbuildable? Evaluate the existing bridge pier. Step 2: Does the alternative meet the secondary project needs, including meeting needs for people walking and biking? Quantitative and qualitative assessment. Corridor and centerline alignment level of detail. Initial assessment of social, economic and environmental impacts. Step 3: Quantitative and qualitative assessment. Preliminary design alyout level of detail. Detailed assessment of social, economic and environmental impacts. Bridge type study.
Click image for larger version

A three-step process is being used to evaluate bridge crossing alternatives and select a preferred project alternative for the Osceola Bridge. This process began with identifying a reasonable range of build concepts, including a no-build alternative. Each step refined the alternatives through quantitative and qualitative environmental analysis. Each step looked at the remaining alternatives at a progressively greater level of detail. The outcome of the third step is the identification of a preferred alternative, which is the alternative that will proceed into final design and ultimately construction for the Hwy 243 Osceola Bridge project.

Bridge concepts were evaluated using the criteria outlined in the Alternatives Evaluation Criteria document. Initial criteria include Bridge Condition and Structure Robustness. Additional criteria include bikeability/walkability, Social, Economic and Environmental considerations, and other factors like constructability and ability to reduce traffic impacts during construction.

Screening process

Identified reasonable range of build concepts A through G, including a no build alternative. Four concepts were removed after first screening for not meeting the project criteria. Remaining concepts in step 2 include B through D and a no build alternative.
Click image for larger version

There were eight concepts screened in step 1. Four of these initial concepts were removed after the first screening for not meeting the project criteria. The Step 2 analysis looked at the remaining 4 build alternatives, which included the option of doing nothing also known as the “no-build” concept. The results of the Step 2 analysis, which were presented to the public in 2022, indicated that there was not adequate information at that level of design to differentiate among the four remaining build alternatives to justify eliminating any of them. Therefore, all four build alternatives considered in Step 2 were carried forward for further evaluation in to Step 3. In Step 3, the “no-build” and three build alternatives were evaluated in greater detail. The project team is now finished with the more extensive step 3 study, where we have taken a refined assessment of the three alignments.

Build alternative B, existing alignment
Shows alternative B, including construction limits, proposed and existing road, and path for people walking or biking.
Click image for larger version
Shows cross section for alternative B on Minnesota side, including construction limits, proposed and existing road, and path for people walking or biking.
Minnesota side
Click image for larger version
Shows cross section for alternative B on Wisconsin side, including construction limits, proposed and existing road, and path for people walking or biking.
Wisconsin side
Click image for larger version

Build alternative C, north alignment
Shows alternative C, including construction limits, proposed and existing road, and path for people walking or biking.
Click image for larger version
Shows cross section for alternative C on Minnesota side, including construction limits, proposed and existing road, and path for people walking or biking.
Minnesota side
Click image for larger version
Shows cross section for alternative C on Wisconsin side, including construction limits, proposed and existing road, and path for people walking or biking.
Wisconsin side
Click image for larger version

Build alternative D, south alignment
Shows alternative D, including construction limits, proposed and existing road, and path for people walking or biking.
Click image for larger version
Shows cross section for alternative D on Minnesota side, including construction limits, proposed and existing road, and path for people walking or biking.
Minnesota side
Click image for larger version
Shows cross section for alternative D on Wisconsin side, including construction limits, proposed and existing road, and path for people walking or biking.
Wisconsin side
Click image for larger version

Step three is being completed

The project team is completing step three, which involves extensive evaluation of the remaining alternatives including a more detailed and refined assessment of the road design and structure. The team will consider geology, trails and road width and the impacts to the St. Croix River, the Wilke Glen Cascade Falls area and area bluffs. A visualization will be created for each of the three alternatives.

Once step three evaluation is complete, another public meeting will be held to share the results and gather input from the public and regulating agencies on the recommended preferred alternative.

Concepts considered in step 1

The eight project concepts under consideration in step 1: Concept A rehabilitation, concept b existing alignment, concept c north alignment, concept d south alignment, concept e 2nd avenue alignment, concept f new alignment, concept g tunnel and a no-build alternative.
Click image for larger version

A total of eight project concepts were considered in step 1 of the process. These alternatives are included on the map below. Descriptions follow.

  • No-Build Alternative: The No-Build Alternative (or “do nothing” alternative) includes routine bridge maintenance activities on the existing Hwy 243 Bridge. The existing bridge deck, superstructure, and piers would be left as-is.
  • Build Concept A: Concept A includes removal of the existing Hwy 243 bridge deck and superstructure and replacement with a new deck and superstructure. The existing bridge
    piers would remain-in-place and be re-used with the rehabilitation concept.
  • Build Concept B: Concept B includes removing the existing Hwy 243 Bridge and constructing a new bridge and approach roadways along the existing alignment.
  • Build Concept C: Concept C includes constructing a new bridge parallel to the existing Hwy 243 bridge. The new bridge would be built to the north of the existing bridge. The existing Hwy 243 Bridge would be removed following construction of the new bridge.
  • Build Concept D: Concept D includes constructing a new bridge crossing parallel to the existing Hwy 243 bridge. The new bridge would be built to the south of the existing bridge. The existing Hwy 243 Bridge would be removed following construction of the new bridge.
  • Build Concept E: Concept E includes constructing a new bridge crossing north of the existing Hwy 243 bridge and realigning Hwy 23 on the Wisconsin Side to connect to the existing 2nd Avenue. The existing Hwy 243 Bridge and approach would be removed following construction of the new bridge.
  • Build Concept F: Concept F includes constructing a new bridge crossing along an entirely new Hwy 243 alignment between MN Hwy 95 and WI Hwy 35 outside of the Village of Osceola. The existing Hwy 243 Bridge would be removed following construction of the new bridge.
  • Build Concept G: Concept G includes constructing a tunnel under the St. Croix River along the existing Hwy 243 alignment from Minnesota to Wisconsin. The existing Hwy 243 Bridge would be removed following construction of the tunnel.