I-94

Oakdale, Woodbury, Landfall, Lake Elmo, Afton and Lakeland

Traffic impacts

-94 between Hwy 120/Century Avenue and the St. Croix River project area map.

I-94 Oakdale to Lakeland project area map
Click image for larger version

All traffic impacts are tentative and weather dependent.

Current

Lane closures

5 a.m. Mon, July 18 through late October
  • EB I-94 is reduced to two lanes between Woodbury Dr. and the St. Croix River

Upcoming

Information about upcoming traffic impacts will be posted as details become available.

Lane closures

Sun, Aug. 14 through Sun, Aug. 21; 8 p.m. to 7 a.m. nightly
  • EB I-94 is reduced to one lane between the St. Croix River and Woodbury Dr.

Ramp closures

Sun, Aug. 14 through Sun, Aug. 21; 6 p.m. to 5 a.m. nightly
  • The following ramps are closed:
    • Woodbury Dr. to EB I-94
    • EB I-94 to Manning Ave. N.
    • Manning Ave. N. to EB I-94
    • EB I-94 to Hwy 95/St. Croix Trail N.

About this project

A large pavement project on I-94 between Hwy 120/Century Ave. and the St. Croix River will begin in July 2022. This project work is anticipated to take two and a half years to complete.

Summary of work

  • Resurface pavement and ramps
  • Construct new eastbound lane from I-494 to Woodbury Dr.
  • Resurface frontage road (Hudson Rd.) in the project area
  • Upgrade pedestrian/bicycle accessibility
  • Repair drainage
  • Replace signage
  • Upgrade lighting
  • Install median barrier