Current and upcoming roadwork
In progress
- 2024-2026: Hwy 10/75 and 11th Street underpass in Moorhead - Portions of First Avenue N and 11th Street closed. Follow detours.
- I-94 Alexandria to Osakis - Crossovers, head-to-head traffic. Travel with caution
- I-94 Red River Bridge in Fargo/Moorhead - Lane shifts/closures. Construction led by NDDOT.
- I-94 bridge replacements near Ashby - Lane closures, then head-to-head traffic starts May 5.
Up next - Starting soon
- Hwy 59/108 Pelican Rapids - Starts May 2. One-lane traffic on Hwy 59. Obey automated signal.
- Highway 114 Lowry to I-94 - Starts May 12. Road closed for culvert work. Thru-traffic detour, local traffic only with restrictions at culvert sites.
- I-94 Rothsay to Fergus Falls - Starts May 19. Lane closures, then crossovers, head-to-head traffic.
- I-94 Moorhead communications upgrades - Starts May 13. Shoulder closures, short-term day-time lane closure, night work with lane closures.
Upcoming in 2025
- Hwy 29/3rd Avenue- Lane closures for pedestrian improvement project start in September 2025.
- Hwy 108 Henning - Pavement repairs, lane closures in summer 2025
Other traffic impacts
Check out 511mn.org for other traffic impacts in west central Minnesota and across the state.
All construction activities and traffic impacts are weather dependent and subject to change. MnDOT urges motorists to always be attentive, drive with caution, slow down in work zones where workers are present, and never enter an area that's blocked by barriers or cones.