Map showing two stages of project
The project will be constructed in two stages. View full-size project area map (JPG).
Map showing truck detour route
The project will require a detour utilizing Roseau County roads 4 and 23. View full-size project detour map (JPG).

Project elements

  • Pavement reconstruction
  • Sidewalk reconstruction
  • Storm sewer reconstruction
  • Corridor lighting
  • Utility improvements
  • Tree/brush removal

Project staging

Staging information and detour route are subject to change. Estimated durations and detour are as follows.

A detour will be used for the duration of the project. Traffic will detour onto Roseau County roads 4 and 23. Local traffic can use city streets to avoid the road closure.

Stage 1

Hwy 11 will be closed between the east side of 4th St to west side of Hwy 32 intersection (Approximately 5 weeks)

Work to be completed in Stage 1
  • Install storm sewer on Hwy 11
  • Install storm sewer outlet to South Branch Two Rivers
  • Reconstruct Hwy 11
  • Sidewalk reconstruction
  • Install bases for corridor lighting

Stage 2

Hwy 11 will be closed between the west side of 7th St to the east side of 4th St (Approximately 7 weeks)

Work to be completed in Stage 2
  • Install storm sewer on Hwy 11
  • Reconstruct Hwy 11
  • Sidewalk reconstruction
  • Install bases for corridor lighting

Stay informed

Stay informed during the project by signing up for email updates.

Nearby projects

Work Zone safety tips

  • Obey posted speed limits
  • Drive undistracted
  • Move over-Give workers room to safely complete their work.
  • Know before you go: 511mn.org
  • Be patient.
  • Do the zipper merge
  • Avoid making unnecessary lane changes
  • Never enter a road blocked with barriers or cones
  • Expect work zones to constantly change