About the project
Highway 11 is in need of long-term improvements to address safety and aging infrastructure. Construction was originally planned for 2025 but was moved to 2026. When complete the project will:
- Replace deteriorating pavements
- Realign the section near the Roseau Airport
- Replace culverts
- Construct right turn lanes and center left turn lane
Roseau area improvements
Three concepts were evaluated for airport safety, vehicle safety, safety of the highway system, environmental impact, construction costs, public input and property acquisition.
Concept 2 was selected as it increases safety with better sightlines and allows for a consistent 60 mph speed limit.
- Concept 1- Although it would allow for a straight road, it ultimately isn't a viable option, as it would keep the road within the airport runway clear zone which goes against FAA and Aeronautics safety requirements
- Concept 2- It satisfies the runway clear zone requirements and improves safety by removing the existing 45 mph curves
- Concept 3- Also satisfies the runway clear zone requirements, but requires increased costs in construction and land acquisition
Recommended design
Warroad area improvements
The 2016 Hwy 11 Corridor Study identified safety concerns in this area related to a lack of turn lanes and too many access points. The recommended design through the "ridge" area near Warroad will include:
- A continuous center left-turn lane
- Realigning skewed intersections at 349th Ave, 350th Ave and 560th Ave to provide a safer 90-degree intersection with Hwy 11
- First Lakewood Ave will be realigned to line up directly across from Pine Ridge Rd